Selected GESU projects, each with its own detail page: location, year, installed system and capacity. Engineering, in-house equipment manufacturing and installation carried out by GESU from Bursa, Türkiye.
20 project pages · 7 abroad (Ethiopia · Iraq · Turkmenistan · Morocco · Philippines · Ukraine)
Maret Tuzla plant — outlet sample analysis

These 20 pages cover a part of our work. The full list of 150 reference jobs (plants and equipment) — each with contract year and location — is on the references page. The 500+ projects figure used on this site is a broader count that also covers equipment supply, revision and expansion works.
Most cards below open the project’s own detail page; the two cards marked «Sector page» open the sector page where that job is described.
Sector
Technology
Country / Region

Namet Gümüşova Integrated Meat Plant — Wastewater Treatment and Water Reuse
Photo: the customer’s earlier plant in Çayırova — not a frame from the Gümüşova site.
Erection in progress — commissioning planned for end of 2026One of the world’s major integrated meat plants. GESU is building a DAF pre-treatment + Kubota flat-sheet MBR chain; once commissioned, the RO at the outlet will recover water for boiler feed and cooling water — not as drinking water. Erection is under way; commissioning is planned for the end of 2026.

Beko-Arçelik Eskişehir Refrigerator Factory — Full Revamp & Water Recovery
Commissioning planned to be completed in September 2026The factory’s existing industrial and domestic wastewater treatment plants were revised from end to end; the water recovery system is being built from scratch as two separate lines — once commissioned, industrial and domestic water will be recovered separately. Commissioning is planned to be completed in September 2026.

Slaughterhouse Wastewater Treatment Plant — Morocco
A slaughterhouse wastewater treatment plant we built turnkey in Morocco. The DAF + biological treatment chain for bloody, greasy slaughterhouse wastewater is in operation on site.

Vero Food Plant — Packaged Domestic Wastewater Treatment, Antalya
Packaged domestic wastewater treatment system for the Vero Gıda plant (2022).

Aynes Dairy Factory — Biological Treatment Plant, Denizli (2,000 m³/day)
Industrial biological treatment plant for dairy processing wastewater (2021). The DAF unit, drum screen and decanter are GESU-manufactured.

Aali Albasiqat, Baghdad — Treatment Plant and Equipment Package
Treatment plant plus a GESU-manufactured equipment package (2021): drum screen, compact fine screen, UV disinfection, biofilter and grit separator.

Philippines — Municipal WWTP Equipment Package (WATERMATIC)
Process design and a GESU-manufactured equipment package for a municipal (domestic + septic) wastewater treatment plant in the Philippines: screens, DAF, SBR equipment, sludge dewatering, sand filter, automation. Client WATERMATIC; ordered 2020, commissioned 2021.

Turkmenistan — Municipal Treatment & Gas Scrubbing
Buysan Gurluysk municipal wastewater treatment plant (2014): the process design and the equipment manufacturing are GESU’s; most of the concrete works were completed, while mechanical erection and commissioning have not been carried out yet. Also the Tejen Ahal gas scrubbing (scrubber) project.

Martur Automotive Supplier — Wastewater Treatment, Bursa
Industrial chemical wastewater treatment plant (2012). Water reuse with activated carbon filtration and RO.

AXOR Industry Alkaline Zinc Plating — Chemical Treatment Plant, Ukraine
Chemical wastewater treatment plant and sludge dewatering system for an alkaline zinc plating line (contract 2011). GESU’s first project in Europe.
Wahat Al Ganop, Iraq — Municipal Wastewater Treatment (120,000 m³/day)
Turnkey municipal/industrial wastewater treatment project (2012).

Akşeker Integrated Meat Plant — Addis Ababa, Ethiopia
Turnkey industrial biological treatment plant + UV disinfection for an integrated meat plant (2012).

Şişecam Trakya Cam Glass Factory — Wastewater Treatment, Mersin
Industrial chemical treatment for glass production wastewater (2011).

Çayırova Boru Galvanising Line — Wastewater Treatment, Kocaeli
Industrial chemical treatment plant for pipe production and galvanising line wastewater (2010).

Dört Mevsim Integrated Meat Plant — Balıkesir
Industrial biological treatment plant for slaughterhouse wastewater (2007). DAF pre-treatment + activated sludge process.

ARTUR Holiday Resort — Municipal-Scale Biological Treatment Plant (1,600 m³/day)
Biological treatment plant of 1,600 m³/day (8,000 population equivalent) and sludge dewatering for the domestic wastewater of a large holiday resort (2000) — our first domestic biological treatment plant.

Konsüt Dairy Products — Biological Treatment Plant
Biological treatment for dairy plant wastewater; basin construction and equipment erection carried out by GESU’s own site team.
SAI Automotive Paint Shop — Wastewater Treatment, Bursa
Industrial chemical treatment plant for automotive surface treatment and paint shop wastewater (2000).

Banvit Red Meat Plant — Physical + Biological Treatment, Bandırma
Physical and biological treatment plant (250 m³/day) and sludge dewatering for red-meat plant wastewater (2009).
Kristal Kola Soft Drink Plant — Packaged Treatment
Packaged treatment unit for beverage bottling wastewater.
Topraklar Dairy Products — Karacabey, Bursa
Industrial biological treatment plant for a milk and dairy products factory (2000).
Durmaz Olive Processing Plant — Gemlik, Bursa
Biological packaged treatment plant for olive processing wastewater (1999).
Let's Talk About Your Project