Beko-Arçelik Eskişehir Refrigerator Factory — Treatment Plant Revision and Water Reuse
The factory’s existing treatment plants were revised from end to end; the water recovery system is being built from scratch. Installation is nearly complete; commissioning is planned to be completed in September 2026. In total an investment of nearly €1 million in treatment plus water recovery.
Engineering, in-house equipment manufacturing and installation by GESU — Bursa, Türkiye.







Not stock imagery — every frame is a real site photo of this project, taken during installation.
Two Separate Jobs, One Project
Reading this project correctly matters: the revamp and the water recovery are not the same thing.
1 — Full Revamp of the Existing Plants
The factory’s existing industrial and domestic wastewater treatment plants were overhauled end to end: process, equipment and automation were renewed by GESU.
2 — Water Recovery Built From Scratch
The water recovery system is independent of the existing plants and is being built from scratch — once commissioned, industrial and domestic water will be recovered on two separate lines and the treated water will go back into production. Commissioning is planned to be completed in September 2026.
Installation of the line is nearly complete; commissioning is planned to be completed in September 2026.
Project data
GESU carries out engineering, equipment manufacturing and installation under one responsibility; most equipment is produced in our own factory in Bursa (5,000 m² total, 2,000 m² covered). Effluent values depend on the characteristics of the incoming wastewater and are established after analysis.