⭐ MAJOR PROJECT · WATER RECOVERY COMMISSIONING SEPTEMBER 2026

Beko-Arçelik Eskişehir Refrigerator Factory — Treatment Plant Revision and Water Reuse

The factory’s existing treatment plants were revised from end to end; the water recovery system is being built from scratch. Installation is nearly complete; commissioning is planned to be completed in September 2026. In total an investment of nearly €1 million in treatment plus water recovery.

Engineering, in-house equipment manufacturing and installation by GESU — Bursa, Türkiye.

Pressure filter tank line and piping during installation — February 2026
Pressure filter tank line and piping during installation — February 2026. Real site photo, not stock.
Pressure filter tanks, valve group and yellow service platform — February 2026
Pressure filter tanks, valve group and service platform — piping completed (February 2026).
RO membrane housings, flow meters and automatic valves — February 2026
RO membrane housings, flow meters and automatic valves — the water recovery line (February 2026).
RO water recovery skid built from scratch — membrane housings, automatic valve and flow meter
RO water recovery skid — during installation. Membrane housings, automatic valves and measurement instrumentation — the heart of the line being built from scratch.
RO membrane line and service platform — water recovery system
Membrane line and service platform — during installation. RO housings, stainless piping and maintenance access.
Pressure filter tanks and automated valve group
Pressure filter tanks — during installation. The filtration stage with its automated valve group.
Filter tank line, wide angle — erection stage
During erection. Installation of the filter line — the valve actuators are still in their protective boxes.

Not stock imagery — every frame is a real site photo of this project, taken during installation.

Two Separate Jobs, One Project

Reading this project correctly matters: the revamp and the water recovery are not the same thing.

1 — Full Revamp of the Existing Plants

The factory’s existing industrial and domestic wastewater treatment plants were overhauled end to end: process, equipment and automation were renewed by GESU.

2 — Water Recovery Built From Scratch

The water recovery system is independent of the existing plants and is being built from scratch — once commissioned, industrial and domestic water will be recovered on two separate lines and the treated water will go back into production. Commissioning is planned to be completed in September 2026.

FROM THE REVISED TREATMENT LINE
Factory wastewater Rotary drum screen Chemical conditioning Circular settling Sludge dewatering with a decanter centrifuge
FROM THE WATER RECOVERY LINE BEING BUILT FROM SCRATCH
Treated water Pressure filter tanks Cartridge filtration RO membranes Back into production

Installation of the line is nearly complete; commissioning is planned to be completed in September 2026.

Project data

Location
Eskişehir, Türkiye
Installed system
Revision of the existing industrial + domestic WWTPs + 2 separate water recovery lines being built from scratch
Sector
White Goods · Revamp + Two-Line Water Recovery
Contractor
GESU Arıtma Sistemleri San. Tic. Ltd. Şti. — Bursa, Türkiye

GESU carries out engineering, equipment manufacturing and installation under one responsibility; most equipment is produced in our own factory in Bursa (5,000 m² total, 2,000 m² covered). Effluent values depend on the characteristics of the incoming wastewater and are established after analysis.

Need a similar plant?

Send us your wastewater analysis and daily flow — our engineer comes back with a preliminary assessment within 2 business days. The preliminary assessment is free and without obligation.

GESU Arıtma Sistemleri · Bursa, Türkiye · +90 224 483 59 39 · info@gesu.com.tr